A building owner may request,
and the Department may grant, permission to start construction for the footings
and foundations upon submission of construction documents under s. SPS
361.31.
A building owner who has been granted permission to start
construction of the footings and foundations may proceed at the owner's own risk
without assurance that a conditional approval for the building will be
granted.
The department shall review and make a determination
on an application for permission to start construction of the footings and
foundations within 3 business days of receipt of the application and all forms,
fees, construction documents and information required to complete the
review.
If choosing to request permission to start, be sure to answer the questions, as appropriate, in the electronic plan review application.