Compliance Assurance Manual (CAM) Checklist
This checklist is intended to serve as a guide to the manufacturer and inspection/evaluation agency in preparing the Compliance Assurance Manual (CAM) for submittal and approval to participate in the Wisconsin Modular Dwelling Program. The titles and numbers listed below are from the National Institute of Standards and Technology, “Model Documents for Evaluation, Approval, and Inspection of Manufactured Buildings, July 1976,” as adopted by the Wisconsin Administrative Code § SPS 320.24. The following format must be followed and include all of the required information in the submitted CAM.
General Requirements
Name and address of inspection/evaluation agency
Each page stamped APPROVED by inspection/Evaluation agency
Properly indexed
Plant name and location Forms - Copies of all inspection forms, records, checklists, labels, stamps, etc.
Description of building system
Copy of agreement between manufacturer and inspection/evaluation agency or signed statement that such an agreement is in force and includes a statement of no conflict of interest
Revision of Manual - Part V, Section 2 (A)(1)
Procedure for revising manual
Changes coordinated with and approved by inspection/evaluation agency
Submission of revision to Department within 10 days
Formal review of manual every 3 months
Organization Structure - Part V, Section 2(A)(2)
Identify organizational elements responsible for compliance assurance (organizational chart)
Compliance assurance functions independent from production
Statement of responsibility and authority of compliance assurance personnel
Inspection/Evaluation agency compliance assurance relationship
Training and Qualifications - Part V, Section 2(A)(2)(a)
Identify person(s) responsible for directing the compliance assurance program
Qualification and training requirements for compliance assurance personnel
Job description of compliance assurance personnel
Resumes for compliance assurance personnel Training programs by manufacturer or inspection agency, if any
Uniform System of Audits - Part V, Section 2(A)(3)
Audit criteria or checklist for manufacturer
Audit criteria or checklist for inspection/evaluation agency
Submit audit findings to the Department
Frequency of audits
Compliance Records - Part V, Section 2(A)(2)
Personnel responsible for keeping records
Record of inspections performed
Record of test results
Data plate
Minor modifications approvals
Dates of production Complaint information
Control of Changes - Part V, Section 2(A)(5)
Procedure for control of changes to building system or compliance documentation (i.e. checklists etc.)
Personnel responsibility for informing personnel of changes
Control of Working Drawings - Part V, Section 2(A)(6)
Use of working drawings
Review for compliance
Approval by inspection/evaluation agency
Procedure to modify plans
Removal of obsolete plans
Responsibility or method for communication of changes
Serial Number System - Part V, Section 2(A)(7)
Number assignment
When assigned Where located on unit
Control of Labels
Part V, Section 2(B)(8)
Personnel who will have responsibility for release and control of labels
Assigning labels to units
Verification of records for unit
Handling of damaged or misused labels
Control of Procurement - Part V, Section 2(B)(1)
System of selecting materials
Evidence of compliance (i.e. grade stamps, listings, etc.)
Review for compliance with approved building system
Receiving Inspection - Part V, Section 2(B)(2)
Method of evaluating materials and supplies upon receipt
Accept/reject criteria
Protection of Materials- Part V, Section 2(B)(3)
Protection from weather
Protection from physical damage
Protection from adverse conditions
Disposition of Rejected Materials - Part V, Section 2(B)(4)
Method of identification and handling of rejected materials
Procedure for repair or rework
Corrective Action - Part V, Section 2(C)(1)
Identification of non-compliant items
Method of correction of non-compliant items
Identify cause of non-compliance
Testing and Inspection Equipment- Part V, Section 2(C)(2)
Test equipment used
Test procedures
Calibration and test of equipment
Frequency of Inspection - Part V, Section 2(C)(3)
All aspects of construction of every unit inspected by in-plant inspector
All aspects of construction inspected by inspection/evaluation agency (every unit inspected at least once by inspection/evaluation agency)
Adjusting frequency of inspections by inspection/evaluation agency
Criteria for determining adjusting the frequency of inspections
Authority for Compliance Assurance - Part V, Section 2(C)(4)
Authority of in-plant inspector
Authority of inspection/evaluation agency
Provision to inspect all dwellings prior to defective and subsequent to last unit inspected by inspection/evaluation agency
Production Flow Diagrams - Part V, Section 2(C)(5)
Material flow chart
Plant layout Inspection and test done at each station
Mandatory inspection locations
Storage locations
Inspection Checklists - Part V, Section 2(C)(6)
Includes all aspects of construction
Use of checklist on production line
Objective of checklist
Code Compliance Workmanship Standards - Part V, Section 2(C)(7)
Use of manufacturer’s instructions and listing requirements
Reference to applicable Wisconsin codes.
Disposition of Non-Compliant Construction - Part V, Section 2(C)(8)
Method of identification of non-compliant item (red tag, etc)
Removal of identification after correction
Recording of non-compliance
Checking of prior and subsequent units
Final Inspection and Certification - Part V, Section 2(D)(1)
Procedures for final inspection
Proper unit identification and records
Label control records
Correct information check
Handling and Storage - Part V, Section 2(D)(2)
Method of handling units
Protection from elements in storage
Inspection of stored units
Packing and Shipping - Part V, Section 2(D)(3)
Protection against damage
Pre-transit inspection
Transportation - Part V, Section 2(D)(4)
Method of transportation
Pre transit inspection
Installation Control - Part V, Section 2(D)(5)
Information to be provided to local inspector
Foundation and structure requirements described
Utilities
Testing
Field Repairs - Part V, Section 2(D)(6)
Method of determining responsibility
Correction of non-compliance when work is result of work by manufacturer
Reporting of non-compliance relating to inadequate plant inspection
Provision to inspect other units suspected of non-compliant items
Withdrawal of labels from units not in compliance
Permission for Inspection- Part V, Section 2(D)(7)
Signed and notarized permission for the Department to audit records and inspect